Transforming our City Centre

Milestones

  • Armley Gyratory Delivery

    January 2022

     

    -

     

    December 2022

    Armley Gyratory in construction.
  • City Square Highways Delivery

    February 2020

     

    -

     

    December 2022

    City Square highways works in construction
  • Leeds City Rail Station Transformation Phase 1

    July 2022

     

    -

     

    Summer 2024

    Leeds City Rail Station in construction.
  • Corn Exchange Scheme Delivery

    August 2020

     

    -

     

    May 2022

    Highways and public space works around the Corn Exchange in construction.
  • Meadow Lane Scheme Delivery

    August 2020

     

    -

     

    April 2022

    Meadow Lane Greenspace in construction.
  • Final masterplan

    October 2021

     

    -

     

    June 2022

    Gather thoughts relating to the refined masterplan proposals. Begin a process of incorporating final community feedback into the masterplan designs
  • Refined masterplan

    July 2021

     

    -

     

    October 2021

    Gather more detailed community aspirations relating to elements of the refined masterplan proposals.
  • Principles and concepts

    April 2021

     

    -

     

    July 2021

    Gather thoughts, ideas and aspirations for the masterplan to inform design process.